- Abstract:
- It is known that the mode of mining operations is one of the main factors influencing the economic efficiency of deposit development. At the stages of development of design documentation, the order of deposit development is determined in such a way as to ensure the design production capacity with minimum volumes of overburden operations, which in turn determines the scheme of deposit opening. The order of development plays a particularly important role in the development of deposits with two or more working zones. The paper presents the results of the analysis of the mining and geological conditions of the Bey coal deposit, where the development of deposit sections is carried out by two working zones in different groups of seams. Despite the obvious benefit of developing one of the groups of seams, in the long term, such uneven development creates negative conditions for subsequent periods of deposit operation. Based on the analysis results, the main reasons for such a development order are formulated, potential negative consequences are identified and further research objectives are formulated.
- Keywords:
- mining mode, mining procedure, opening scheme, stripping ratio, coal deposit, mining in different working zones
- For citation:
- Kislyakov V.E., Shwartskopf A.V., Fedotov A.S. Study of the influence of mining and geological conditions of the Beyskoye deposit and the mining mode on the opening scheme and the order of development. Mine Surveying and Subsurface Use. 2025;25(5):15-20. (In Russ.). https://doi.org/10.56195/20793332-2025-25-5-15-20
- Information about the authors:
-
- Viktor E. Kislyakov – Dr. Sci. (Eng.), Professor of the Open-pit Mining Department of the Institute of Non-Ferrous Metals of the Siberian Federal University, 660025, Krasnoyarsk, Russian Federation
- Andrey V. Schwarzkopf – PhD student, Department of Open Pit Mining, Siberian Federal University, 660025, Krasnoyarsk, Russian Federation
- Artem S. Fedotov – PhD student, Department of Open Pit Mining, Siberian Federal University, 660025, Krasnoyarsk, Russian Federation; e-mail:
This email address is being protected from spambots. You need JavaScript enabled to view it. ; https://orcid.org/0009-0005-9552-2956
- References:
-
- 1. Кортелев О.Б., Ческидов В.И., Норри В.К. Влияние параметров рабочей зоны на режим горных работ и границы карьеров. Физико- технические проблемы разработки полезных ископаемых. 2011; 5: 53-59. Kortelev O.B., Cheskidov V.I., Norri V.K. Influence of working area parameters on the mining mode and quarry boundaries. Physical and technical problems of mineral development. 2011; 5: 53-59. (In Russ.).
- 2. Таланин В.В., Бехер В.Г., Казаков В.А. Особенности регулирования режима открытых горных работ в условиях волатильности рын ка угля. Горный информационно-аналитический бюллетень (научно-технический журнал). 2023; 5: 142-154. Talanin V.V., Bekher V.G., Kazakov V.A. Features of regulation of open-pit mining mode in conditions of coal market volatility. Mining information and analytical bulletin (scientific and technical journal). 2023; 5: 142-154. (In Russ.). https://doi.org/10.25018/0236_1493_2023_5_0_142.
- 3. Канзычаков С.В., Лапаев В.Н., Соколовский А.В. Развитие горных работ на разрезе: методический подход к управлению. Вестник МГТУ им. Г. И. Носова. 2012; 3: 73-76. Kanzychakov S.V., Lapaev V.N., Sokolovsky A.V. Development of open-pit mining operations: a methodological approach to management. Bulletin of Nosov Moscow State Technical University. 2012; 3: 73-76. (In Russ.).
- 4. Холодняков Д.Г., Логинов Е.В. Управление режимом горных работ и углом откоса рабочего борта карьера. Горный информационно- аналитический бюллетень (научно-технический журнал). 2015; 2: 71-74. Kholodnyakov D.G., Loginov E.V. Management of mining operations and the slope angle of the working side of the quarry. Mining information and analytical bulletin (scientific and technical journal). 2015; 2: 71-74. (In Russ.).
- 5. Черепанов Е.В. Обоснование технологии горных работ на рудных карьерах, имеющих отставание по вскрыше. Сибирский аэрокосмический журнал. 2006; 5 (12): 267-270. Cherepanov E.V. Justification of mining technology at ore quarries with a lag in overburden. Siberian Aerospace Journal. 2006; 5 (12): 267-270. (In Russ.).
- 6. Косолапов А.И., Черепанов Е.В. О технологических возможностях управления вскрышными работами на рудных карьерах. Горный информационно-аналитический бюллетень (научно-технический журнал) 2013; 7: 40-46. Kosolapov A.I., Cherepanov E.V. On the technological capabilities of managing overburden operations at ore quarries. Mining information and analytical bulletin (scientific and technical journal). 2013; 7: 40-46. (In Russ.).
- 7. Зейтинова Ш.Б., Италмасова А.Р. Регулирование режима горных работ за счет применения временных отваловТ. руды университета. 2020; 1 (78): 159-163. Zeitinova Sh.B., Italmasova A.R. Regulation of the mining mode through the use of temporary dumps. Proceedings of the University. 2020; 1 (78):159-163. (In Russ.).
- 8. Сысоев А.А., Литвин Я.О. О планировании объемов автомобильной вскрыши для размещения во временных отвалах. Вестник КузГТУ. 2011; 4: 45-47. Sysoev A.A., Litvin Ya.O. On planning the volumes of automobile cuttings for placement in temporary dumps. Bulletin of KuzSTU. 2011; 4: 45-47. (In Russ.).
- 9. Косолапов А.И., Кисляков В.Е., Федотов А.С., Шварцкопф А.В. Условия и проблемы разработки Бейского месторождения каменного угля. Маркшейдерия и недропользование. 2025; 1: 25-29. Kosolapov A.I., Kislyakov V.E., Fedotov A.S., Schwarzkopf A.V. Conditions and problems of development of the Beyskoye coal deposit. Mine surveying and subsoil use. 2025; 1: 25-29. (In Russ.).
- 10. Еременко Е.В., Косолапов А.И. К вопросу управления техногенным ресурсом карьера. Горный информационно-аналитический бюллетень (научно-технический журнал). 2015; 1-1: 249-259. Eremenko E.V., Kosolapov A.I. On the issue of quarry technogenic resource management. Mining information and analytical bulletin (scientific and technical journal). 2015; 1-1: 249-259. (In Russ.).
- 11. Еременко Е.В. Обоснование направления развития фронта горных работ на основе закономерностей формирования техногенного ресурса. Горная промышленность. 2016; 3 (127): 86-88. Eremenko E.V. Justification of the direction of development of the mining front based on the patterns of formation of the technogenic resource. Mining industry. 2016; 3 (127): 86-88. (In Russ.).
- 12. Селюков А.В. О технологической значимости внутреннего отвалообразования при открытой разработке угольных месторождений Кемеровской области. Физико-технические проблемы разработки полезных ископаемых. 2015; 5: 23-34. Selyukov A.V. On the technological significance of internal waste dumping during open-pit mining of coal deposits in the Kemerovo region. Physical and technical problems of mineral development. 2015; 5: 23-34. (In Russ.).
- 13. Ракишев Б.Р., Молдабаев С.К. Оптимальное распределение объемов вскрышных пород между внешним и внутренним отвал ами в пределах карьерного поля. Горный информационно-аналитический бюллетень (научно-технический журнал). 2012; 9: 47-55. Rakishev B.R., Moldabaev S.K. Optimal Distribution of Overburden Volumes between External and Internal Dumps within a Quarry Field. Mining information and analytical bulletin (scientific and technical journal). 2012; 9: 47-55. (In Russ.).
- 14. Селюков А.В. Оценка численного моделирования процесса адаптации внутреннего отвалообразования к режиму действующих карьерных полей Кемеровской области. Известия ТПУ. 2015; 12: 60-71. Selyukov A.V. Evaluation of Numerical Modeling of the Adaptation Process of Internal Dumping to the Regime of Operating Quarry Fields in Kemerovo region. TPU Bulletin. 2015; 12: 60-71. (In Russ.).
- 15. Радченко С.А., Левченко Я.В. Формирование вскрышных грузопотоков при отработке крупных угольных брахисинклиналей. Горный информационно-аналитический бюллетень. 2013; 6: 52-57. Radchenko S.A., Levchenko Ya.V. Formation of Overburden Freight Flows during Development of Large Coal Brachysynclines. Mining Information and Analytical Bulletin. 2013; 6: 52-57. (In Russ.).